Here’s a quick update on the renovation project from the park superintendent: 

The campground bathhouse, the day use restrooms, and the concession stand have been demolished and the foundations for the new facilities have been poured. There should be block work going up over the next few weeks and we should see the new structures begin to go vertical.

All of the new sewer connections have been completed. In the campground, the contractors are working on leveling the campsites. This will take several weeks to complete, as long as the rain holds off! All in all, significant work has been completed at Ebenezer to date. 